From: ROBERT BARBATO 
To: corps.relchg.south@spk-wc.usace.army.mil, people.pnf@spk-wc.usace.army.mil
Subject: Release Change - PNF

Release Notification Generated 20Mar2023 @ 0822.
All flows reported in cfs.
All times reported in local time (UTC-07:00).

    Pine Flat Releases as Follows                   
                           |     From|       To|
Change for 05Mar2023 @ 2300|     3600|     3660|
Change for 06Mar2023 @ 1200|     3660|     4220|
Change for 07Mar2023 @ 0000|     4220|     4920|
Change for 07Mar2023 @ 1200|     4920|     5470|
Change for 07Mar2023 @ 2300|     5470|     5420|
Change for 08Mar2023 @ 0400|     5420|     5360|
Change for 09Mar2023 @ 0000|     5360|     1200|
Change for 10Mar2023 @ 1900|     1200|     6220|
Change for 11Mar2023 @ 1300|     6220|     6000|
Change for 11Mar2023 @ 1400|     6000|     5800|
Change for 13Mar2023 @ 0530|     5800|     1000|
Change for 14Mar2023 @ 1800|     1000|     6175|
Change for 15Mar2023 @ 1100|     6175|     6225|
Change for 15Mar2023 @ 1500|     6225|     6250|
Change for 15Mar2023 @ 2300|     6250|     6850|
Change for 16Mar2023 @ 1200|     6850|     7250|
Change for 17Mar2023 @ 1200|     7250|     7050|
Change for 17Mar2023 @ 2100|     7050|     6950|
Change for 19Mar2023 @ 1200|     6950|     6820|
Change for 20Mar2023 @ 0500|     6820|     7320|
::::::::::::::::::::::::::::::::::::::::::::::::::::
COMMENT: The Order is satisfied by the combination of the
         release from Pine Flat Dam and uncontrolled flows
         from the Mill and Hughes Creeks. During storm events
         the flow from Mill and Hughes Creeks may exceed the
         Order temporarily. Release change made at request of
         Kings River Water Master.
::::::::::::::::::::::::::::::::::::::::::::::::::::